This coming week (June 23-27) the contractor will be finishing the necessary demolition work and will begin prepping to pour the new curbing needed to install new left turn pockets and lengthen existing left turn pockets on Burden Blvd. The contractor will be pouring the curbing later in the week. On Monday and Tuesday (June 23-24) the contractor will be boring under Burden Blvd to install conduit and wire necessary for the new street lights which have already been installed. While this work is being completed there will be lane closures on the inside lanes near the existing medians to accommodate this work.
There will be no lane closures or construction activity during the week of June 30 – July 4 to allow better access for the planned 4th of July festivities.